Al Habtoor Group announced the tower at a groundbreaking ceremony at Al Habtoor City on 11 May 2023. The initial plan was a G+7+73 building of 81 floors with 1,701 units, about 350,000 m² of built-up area and a 36-month completion target. The group said it was aiming for LEED Platinum certification.
— Story
On 24 May 2023 the group named China Railway 18th Bureau Group as main contractor, with Bauer on the piling works. The tower rises above an existing parking basement that serves completed Al Habtoor City buildings, so it is built top-down rather than by demolishing the basement. The topping-out at 86 floors was announced in April 2026, and the developer later reported the installation of the final glass façade panel.